EA Credit 5
EA Credit 5: Measurement & Verification
1 Point

Intent
Provide for the ongoing accountability of building energy consumption over time.

Requirements
  • Develop and implement a Measurement & Verification (M&V) Plan consistent with Option D: Calibrated
    Simulation (Savings Estimation Method 2), or Option B: Energy Conservation Measure Isolation, as specified
    in the International Performance Measurement & Verification Protocol (IPMVP) Volume III: Concepts and
    Options for Determining Energy Savings in New Construction, April, 2003.
  • The M&V period shall cover a period of no less than one year of post-construction occupancy.

Potential Technologies & Strategies
Develop an M&V Plan to evaluate building and/or energy system performance. Characterize the building and/or
energy systems through energy simulation or engineering analysis. Install the necessary metering equipment to
measure energy use. Track performance by comparing predicted performance to actual performance, broken
down by component or system as appropriate. Evaluate energy efficiency by comparing actual performance to
baseline performance.

While the IPMVP describes specific actions for verifying savings associated with energy conservation measures
(ECMs) and strategies, this LEED credit expands upon typical IPMVP M&V objectives. M&V activities
should not necessarily be confined to energy systems where ECMs or energy conservation strategies have been
implemented. The IPMVP provides guidance on M&V strategies and their appropriate applications for various
situations. These strategies should be used in conjunction with monitoring and trend logging of significant
energy systems to provide for the ongoing accountability of building energy performance.